Project Ironwood
Withdrawn or rejectedDundee and Milan Townships, Monroe County
The applicant pulled it, or the municipality refused it and no application is live.
The project
- Electrical demand
- No capacity figure on the record
- Developer
- Cloverleaf Infrastructure
- Serving utility
- DTE Electric
- Site size
- 750 acres
Last checked August 21, 2026. Every field above has been confirmed against the sources listed.
What has happened
Every entry carries the source it came from. Where the record gives no date, the entry says so rather than being placed by guesswork.
- October 2025Cloverleaf withdrew its pre-development agreement after sustained local opposition. Blackridge Research
On the record, but undated
No source consulted gives a date for these, so they are not placed in the sequence above.
- Date not on the recordDundee Township enacted a temporary moratorium. Blackridge Research
Sources
Everything above traces to one of these. Local agendas and FAQ pages get replaced in place rather than archived, so each carries the date it was read.
- [1] Lyon Township data center project profile — Blackridge Research, read August 21, 2026
Watch the docket this project runs through
Large-load contracts, tariff changes and the cases contesting them all arrive as DTE Electric filings. Alerts go out when one is filed and when a comment deadline is set — which is the only window in which a comment counts for anything.