Prologis Washington Township site
Withdrawn or rejectedWashington Township, Macomb County
The applicant pulled it, or the municipality refused it and no application is live.
The project
- Electrical demand
- 760 MWreported estimate
Estimate reported by a third party, not confirmed by the developer
- Developer
- Prologis
- Serving utility
- DTE Electric
- Site size
- 312 acres
- Also on the record
- Withdrawn. No live application remains.
Last checked August 21, 2026. Every field above has been confirmed against the sources listed.
Sources
Everything above traces to one of these. Local agendas and FAQ pages get replaced in place rather than archived, so each carries the date it was read.
- [1] Map of AI data centers in Michigan — EDRA of Michigan, read August 21, 2026
Watch the docket this project runs through
Large-load contracts, tariff changes and the cases contesting them all arrive as DTE Electric filings. Alerts go out when one is filed and when a comment deadline is set — which is the only window in which a comment counts for anything.