University of Michigan / Los Alamos research facility
Pre-applicationYpsilanti Township, with a second site proposed in Superior Township, Washtenaw County
Land assembled, optioned or purchased, or a pre-development agreement signed. Nothing before a planning commission yet.
The project
- Electrical demand
- No capacity figure on the record
- Developer
- University of Michigan with Los Alamos National Laboratory
- End user
- University of Michigan
- Serving utility
- DTE Electric
- Site size
- 144 acres
- Expected online
- Construction targeted for 2027
- Water
- The Ypsilanti Community Utilities Authority said it would not supply cooling water to the Ypsilanti Township site, which prompted the university to propose an alternative site in Superior Township.
- Also on the record
- A roughly 300,000 sq ft facility had been set to break ground in 2026.
Last checked August 21, 2026. Every field above has been confirmed against the sources listed.
What has happened
Every entry carries the source it came from. Where the record gives no date, the entry says so rather than being placed by guesswork.
On the record, but undated
No source consulted gives a date for these, so they are not placed in the sequence above.
- Date not on the recordThe refusal of cooling water at the original site moved the project's likely location. Shoreline Media
What DTE Electric customers pay, before and now
Residential rate, 2019
16.11¢
Residential rate, 2024
20.13¢
Change over that period
+25%
Those figures are DTE Electric’s own EIA-861 filings and they cover the whole territory. This page does not attribute any part of that change to University of Michigan / Los Alamos research facility. It could not honestly: the change spans years in which this project did not exist, rates move for generation costs, storm recovery, tree trimming and approved return on equity all at once, and the large-load terms the Commission has approved are written specifically to keep these costs off other customers’ bills. Whether they succeed is an open question in front of the Commission, not a settled fact this site can assert.
The terms a large load takes service under here
DTE Electric operates under U-21990, approved December 18, 2025. Approved special contracts for electric service to the Saline Township data center, with conditions — a contract-by-contract approval rather than a general tariff.
- Contracted demand
- Roughly 1,383 MW.
- Contract length
- A power supply agreement of roughly 19 years, extendable by the customer for a further 20, plus a separate 15-year energy storage agreement.
- Conditions imposed
- Cost allocation and rate design proposals ensuring future large-load interconnection customers pay their own interconnection costs, plus an administrative fee for further large loads.
The Attorney General's motion to reopen and her separate petition for rehearing were both denied on 27 March 2026. On 17 April 2026 she filed a claim of appeal in the Michigan Court of Appeals, seeking to invalidate the approval as an unlawful ex parte order and to remand the matter for a contested case hearing. The proceeding is not closed.
- Michigan Public Service Commission: MPSC approves DTE Electric energy contracts for data center with conditions to strengthen protections for other customers
- Michigan Department of Attorney General: Attorney General’s Efforts to Review DTE Data Center Contracts Rejected Again At MPSC
- Michigan Department of Attorney General: AG Nessel Files Appeal of MPSC Approval of DTE’s Saline Data Center Contracts
Sources
Everything above traces to one of these. Local agendas and FAQ pages get replaced in place rather than archived, so each carries the date it was read.
- [1] Why data centers, and why Michigan? — Shoreline Media, read August 21, 2026
- [2] How many AI data centers are planned in Michigan? We counted. — Gander Newsroom, read August 21, 2026
Watch the docket this project runs through
Large-load contracts, tariff changes and the cases contesting them all arrive as DTE Electric filings. Alerts go out when one is filed and when a comment deadline is set — which is the only window in which a comment counts for anything.